Construction Updates

Kirkwood Road Project

Posted On: May 1, 2017
Construction Start: May 15, 2017
Anticipated Construction Completion: September 2017
Contractor: Precise Services Inc
Estimated Construction Cost: $382,000.00
Project Manager: Byron Acevedo
Project Scope:

The project scope includes pavement widening and signal modification at S. Kirkwood Road at US 59 NB Frontage Rd. Scope includes installation of a new signal at S. Kirkwood and Greenbriar road. This mobility project will improve traffic flow along Kirkwood Road.

Latest Update:

Expect lane closures and detours for the duration of the project. Two-way traffic will be maintained throughout the project. Inquiries should be directed to the Public Works Department via email at bacevedo@staffordtx.gov or by phone at (281)-261-3921.

Project Schematic:

S. Kirkwood Road at Greenbriar Drive Traffic Signal Layout

S. Kirkwood Road at US 59 NB Frontage Road Pavement Widening Layout

Staffordshire Sidewalks:

Posted On: May 1, 2017
Construction Start: May 15, 2017
Anticipated Construction Completion: August 2017
Contractor: Millis Equipment LLC
Estimated Construction Cost: $390,000.00
Project Manager: Byron Acevedo
Project Scope:

The scope of the project is to construct sidewalks on the south side of Staffordshire Rd from S. Main to 5th St and north side of Staffordshire Rd from 5th St. to Scanlin Rd. This mobility project will provide safe access for pedestrians between major residential and commercial areas.

Latest Update:

Expect lane closures and detours for the duration of the project. Two-way traffic will be maintained throughout the project. Inquiries should be directed to the Public Works Department via email at bacevedo@staffordtx.gov or by phone at (281)-261-3921.

Project Schematic:

Overall Project Layout